2023 to Present

  • Ongoing projects for captive power plant, rolling mill and steel melting shop at Angul
  • Project Evaluation for DRI at Anra Plant with WHRB captive power plant
  • Start of 2nd Pellet plant at Anra
  • Start of Benefication plant at Anra

2018-2022

  • Start of Operations of DRI and production of Sponge Iron at Angul Plant
  • Enhanced production capacity of Khanbandh Iron Ore Mines to 1.5 Mn tons per annum
  • Sree Metaliks shows continuous growth in revenues & crosses turnover of Rs. 1500 Crore
  • Commissioning of Pulverized Coal Injection (PCI) at Anra
  • Modernisation in operations at Loidapada & Anra Plants
  • Commissioning of new Oxygen Plant – 125 THP, having a capacity of 400 cylinders per day
  • Commencement of commercial operation at Captive Iron Ore Mines, Khanbandh

2011-2017

  • Lease of Captive Iron Ore mines at Khanbandh executed with Government of Odisha
  • Commencement of commercial operation at Captive Iron Ore Mines, Khanbandh

2006-2010

  • Commenced production of 200 TPD capacity Rolling Mill for TMT bars at Loidapada under License from Thermax Quenching System Technology, Germany
  • 20 MW Captive Power Plant set up at Loidapada
  • SML House inaugurated at Barbil, Odisha
  • Single Window Clearance granted by Government of Odisha for a Integrated Steel and Benefication Plant at Anra
  • Commencement of construction work for 0.6 MTPA Pellet Plant (Phase1) at Anra
  • MoEF, GOI Anra, Keonjhar granted Environment Clearance for Integrated Steel Complex at Anra
  • Commenced Commercial Operation of 0.6 MTPA Pellet Plant at Anra
  • Having achieved the targeted productions in a very short span, Government enhances the capacity of the Integrated Steel Plant at Barbil from 0.25 MTPA to 0.70 MTPA

2001-2005

  • 5th Sponge Iron Kiln commenced operations at Loidapada Plant
  • 6th Sponge Iron Kiln commenced operations at Loidapada Plant
  • 1st Mini Blast Furnace of 100 TPD capacity established at Loidapada Plant, Odisha
  • Commenced operation of 1st Waste Heat Recovery Boiler based 8 MW Captive Power Plant at Loidapada
  • Sree Metaliks signs MOU with Government of Odisha for setting up of an Integrated Steel Complex of 0.25 MTPA capacity at Barbil
  • Commenced operation of two Induction Furnaces (Steel Melting Shop) for making Billets

1995-2000

  • Sree Metaliks Limited incorporated under the Companies Act 1956
  • Production at 1st Mini 50 TPD Sponge Iron Plant commenced at Loidapada, Odisha
  • 2nd, 3rd and 4th Sponge Iron Kiln commenced operations at Loidapada Plant